Default Data Transfer to All Components

Data Transfer to All Components

Use

You can use report RCATSTAL (Time Sheet: Transfer to Target Components) to transfer time sheet records to the following target components in one step:
  • Human Resources (HR)
  • Controlling (CO)
  • Project System (PS)
  • Plant Maintenance/Customer Service (PM/CS)
At present, you cannot use the report to transfer data to Materials Management (MM). To call the report choose Time sheet ® Transfer ® All components.

Integration
  • Report RCATSTAL combines the functions of the data transfer reports for Human Resources, Controlling, Project System, and Plant Maintenance/Customer Service. Any selection options that apply to certain target components only are indicated accordingly.
  • If you have two separate systems installed, for Human Resources (HR) on the one hand and for Logistics and Accounting on the other, you must run the report for transferring data to HR in the HR system. You can then transfer data to Controlling, Project System, and Plant Maintenance/Customer Service in one step in the other system.
Prerequisites

To be able to run the report, you must have

  • Made all the component-specific Customizing settings in the target components
  • Been assigned authorization to execute the relevant HR, CO, PM/CS, and PS data transfer reports
Features

Selection
  • Report RCATSTAL enables you to select data according to your employees' organizational assignment. You can select data for all employees assigned to a specific cost center, for example. This option is not available if you use the separate data transfer reports for the individual target components.